Risks and issues

A risk is something that could go wrong, such as a vendor delivering late. An issue is something that has gone wrong and needs fixing now. Keep both in one place, score risks so the worst stand out, and escalate issues that are not resolved in time.

Before you start

  • Risks and issues are raised inside a project, on its Risks & issues tab. The Planning & control → Risks & issues page shows them across every project you can see.
  • To raise or edit risks you need a role such as Project Manager, Team Leader, QA Engineer or Department Manager. Every member can raise and update issues. The Settings tab is for administrators.
  • Time needed: about 3 minutes per risk or issue.

The risk register and heat map

Open Planning & control → Risks & issues. The Risk register tab shows a heat map on the left and the list of risks on the right.

Risk register with a heat map and the list of risks across projects

1 The heat map of open risks: probability across, impact up. 2 Show one project only.

Each risk has two scores from 1 to 5:

Score 1 2 3 4 5
Probability Rare Unlikely Possible Likely Almost certain
Impact Negligible Minor Moderate Major Severe

Severity = probability × impact (1 to 25). The severity falls into a band: Low (1–4), Medium (5–9), High (10–14) or Critical (15–25). Your administrator can change where the bands start.

How to use the register:

  • Click a heat-map cell to list only the risks with that probability and impact. Click Clear cell filter to see them all again.
  • Show: choose Open and monitored (the default), All, Closed or Occurred.
  • Read the columns: Severity (an arrow shows whether it went up or down at the last assessment), P × I, Status, Owner, Strategy, Actions (done/total, with a red mark if one is overdue) and Review (red when the risk is due for review).
  • Open a risk: click its row.

Raise a risk

  1. Open the project and click the Risks & issues tab. Make sure Risk register is selected, then click Raise risk.

    Risks & issues tab of a project with the Raise risk button
    1 Raise risk. 2 Switch between Risk register, Issues and Reports for this project.

  2. Fill in the risk. Only the title, probability and impact are needed; the severity is calculated as you click.

    Raise a risk window
    The Raise a risk window.

    Field What to enter Example
    Risk What could happen, in one sentence. RBI security audit finds gaps in the MPIN login
    Probability and Impact Click 1–5 for each. Hover over a number to see its meaning. 3 (Possible) × 5 (Severe) = 15, Critical
    Category From your organisation's list. Security
    Owner The person who watches the risk. Rahul Verma
    Cause Why it could happen. The bank audits every release against RBI guidelines
    Trigger The early warning sign that it is happening. Audit checklist arrives with more than five open points
    Response Avoid (change the plan so it cannot happen), Transfer (insurance, contract, supplier), Mitigate (reduce probability or impact), Accept (keep a contingency) or Escalate (hand it to a higher level). Mitigate
    Mitigation plan What you will do to reduce it. Internal VAPT in sprint 3
    Contingency (if it happens) Plan B. Release Android first
    Next review When to look at it again. Default: in 14 days. 1 Dec 2026
  3. Click “Raise risk”. The risk gets a number such as SBANK-R1 and opens so you can add actions.

Work on a risk

Click a risk to open it.

An open risk with its actions

A critical risk with two mitigation actions; one of them is overdue.
  • Change the details on the left and click Save changes. When you change the probability or impact, type an Assessment note; it is kept in the Score history tab.
  • Add mitigation actions on the Actions tab: type the action, choose an Assignee and a Due date, and click Add. Each action becomes an ordinary work item in the project, so it appears in the person's Tasks and on the board.
  • Reviewed, no change: click it after a review when nothing has changed. The next review date moves forward.
  • Monitor: the risk is under control but you keep watching it (status Monitoring).
  • Close risk: it can no longer happen. Reopen brings it back.
  • Risk occurred…: the risk has happened. The ERP asks for the issue's title, priority, impact, owner and resolution date, then creates an issue linked to the risk (the risk status becomes Occurred).
  • Activity shows who changed what.

The issue log

The Issues tab lists problems that need action now.

Issue log with priorities, escalation levels and resolution dates

The issue log. Above the list the ERP counts issues past the resolution date and escalated ones.
Column Meaning
Issue Number and title. Blocks N means it blocks N open items; From …-R1 means it came from a risk that occurred.
Priority Low, Medium, High or Urgent.
Status Open, In progress, Resolved or Closed, plus the escalation Level if it was escalated.
Resolve by The target date; red with a mark when it has passed.
Age Days since it was raised.

Use Show to choose Open, All, Resolved or Closed.

Raise an issue

  1. In the project's Risks & issues tab, click Issues, then Raise issue.

    Raise an issue window
    The Raise an issue window.

  2. Enter the Issue (what went wrong), the Priority, the Owner who will fix it, the Resolve by date, the Impact (what it affects: deadlines, cost, people, customers) and a Description.

  3. Click Raise issue.

Work on an issue

An urgent issue with its history and a blocked item

An urgent issue that is past its date, escalated to level 1 and blocking the regression test.
  • Start work moves it to In progress.
  • Comment in the History card on the right; every status change and escalation is listed there too.
  • Block items: in Blocked items, search for a project item and click Block. While the issue is open those items are marked Blocked and cannot be submitted for review. Resolving the issue unblocks them.
  • Escalate raises the issue to the next level (up to 3), with an optional reason. The escalation rules can also do this automatically (see Escalations).
  • Resolve… asks how it was resolved (required). Close it afterwards, or Reopen it if the problem returns.

Risk and issue reports

The Reports tab (on the organisation page and inside each project) summarises everything.

Risk reports: KPIs, heat map, top risks, exposure trend and issues per week

Reports across all projects. A yellow bar warns about risks due for review and overdue mitigation actions.
Part What it shows
Open risks Count, with how many are critical and high.
Exposure The sum of the open risks' severity. A rising exposure means risk is building up.
Open issues Count, with how many are past the date and escalated.
Average resolution Average days to resolve, for issues resolved in the last 90 days.
Heat map and Top risks Click a cell or a row to open the risks.
Risk exposure chart Exposure, open risks and high-or-critical risks at the end of each week.
Issues per week Raised against resolved.
Open issues by age 0–7 days, 8–30, 31–90 and over 90 days, by priority.
By project Risks, high risks, exposure, issues and late issues per project. On the organisation page you can also filter by department.

Settings

Administrators see a Settings tab on the organisation page.

Risk settings: categories and severity bands

The default categories and bands.
  • Categories: the list offered when raising a risk. Type a new one and press Enter, or click × to remove one.
  • Medium from, High from, Critical from: where each severity band starts.
  • Review every (days): the default time until a risk's next review.

Click Save settings.

Common questions

Why can't I see a Raise risk button on the Risks & issues page?

Risks and issues are raised inside a project. Choose a project in the box at the top and click Open the project's register, or open the project and go to its Risks & issues tab.

An issue's priority went up by itself

The escalation rules can raise the priority when an issue stays unresolved past its date. See Escalations.

What is the difference between closing and resolving an issue?

Resolve says the problem is fixed and records how. Close files a resolved issue away. Both stop it from counting as open.

Can the AI suggest risks?

Yes. On the AI assistant page choose a project and click Risks. You review the suggestions and add only the ones you want.