Portfolio and programmes

See every project on one page: health, priority, dates, progress, budget and risks. Group projects into portfolios and programmes, rank them, and link projects that wait for each other so you spot a late hand-over before it hurts.

Before you start

  • You need the Project Management category and permission to read the portfolio. You see only the projects you are allowed to see.
  • To create portfolios and programmes you need permission to manage them; the Portfolios button appears only then.
  • Time needed: about 5 minutes to set up a portfolio.

The portfolio page

Open Projects → Portfolio in the menu.

Portfolio table with five client projects

1 Choose which projects to show. 2 Switch between Table, Roadmap and Risk vs health. 3 Portfolios creates and edits portfolios and programmes.

The four tiles at the top sum up the projects shown:

Tile What it tells you
Projects How many projects are in the list.
Health How many projects are On track (green), At risk (amber) and Off track (red).
Late dependencies How many links between projects are already broken: a project should have started but the project it waits for has not finished. See Link projects that depend on each other.
Budget · forecast The total approved budget of the projects and, in the title, the forecast cost at completion. If you can't see budgets, this tile shows High risks instead.

The Table view lists one row per project:

Column Meaning
# The project's rank in the portfolio (only when you have chosen a portfolio).
Project Code and name. Click it to open the project.
Health On track, At risk, Off track or No health yet, with the health score from 0 to 100. The ERP works it out from the project's live data, such as overdue work, progress and risks.
Priority, Status, Dates From the project's details.
Progress How much of the work is done.
Overdue Open items past their due date.
Risks Open risks; the number in red is how many are high. Point at it to see the risk exposure.
Budget, Forecast, CPI Shown only if you may see budgets. CPI (cost performance index) below 0.90 is red: the project spends more than planned for the work done.
Next milestone The next open milestone and its due date.

Health on the portfolio and on the project

Lists such as the portfolio read a snapshot of health that the ERP refreshes every hour, so a change you just made can take up to an hour to appear here. The project's own page always shows the live value.

Portfolios and programmes

By default the page shows All projects I can see. To look at a smaller set, group projects:

  • A portfolio is any set of projects you want to watch and rank together, for example Client delivery FY 2026-27.
  • A programme is a set of related projects that work towards one goal and often share people, for example Digital channels programme (the bank app and the online store share designers and testers).

Both work the same way in the ERP; the label only tells people what kind of group it is. A project can be in several portfolios.

Create a portfolio

  1. Click “Portfolios” at the top right of the portfolio page. A panel lists the existing portfolios and programmes.

    Portfolios and programmes panel
    Two groups in the example data: a portfolio and a programme.

  2. Click “New”.

  3. Fill in the form.

    Field What to enter Example
    Name (required) A short name. Client delivery FY 2026-27
    Kind Portfolio or Programme. Portfolio
    Description What the group is for. Every client project Nexa delivers this financial year.
    Projects, most important first Pick projects one by one in Add a project. Use the up and down arrows to rank them and the cross to remove one. SBANK first, BRIGHT last

    Editing a portfolio with five ranked projects
    The order of the list is the rank shown in the # column.

  4. Click “Save”. The new group appears in the selector at the top of the page, with the number of projects it holds.

To change a group later, open Portfolios and click Edit. To delete one, click the bin icon; the projects themselves are not touched.

Roadmap view

Choose a portfolio and click Roadmap to see the projects on a timeline.

Portfolio roadmap with project bars, milestones and dependency arrows

Each bar runs from the project's start to its end and is coloured by health; the darker part is the progress. The dashed line is today.
  • A diamond is a milestone. A grey diamond has been reached. Point at it to see its name and date.
  • An arrow links two projects that depend on each other. A red arrow is a late dependency.
  • Below the chart, every dependency is listed with its slack (days to spare) or how many days it is late.
  • Projects without dates are left off the chart; a note under the legend says how many.

Risk vs health view

Click Risk vs health to compare projects in one chart. Each bubble is a project:

  • Across is the risk exposure: the sum of probability × impact of its open risks.
  • Up is the health score.
  • The size is the number of open items, and the colour is the health.

Risk vs health bubble chart

Projects at the bottom right need attention first: poor health and high risk. Point at a bubble to see which project it is.

Risks come from each project's risk register; see Risks & issues.

Sometimes one project can't start until another has finished, for example because the same engineer moves from one to the other. Record this on the project that waits.

  1. Open the project that waits and stay on its Overview tab.
  2. Find the “Project dependencies” card and click Add.

    Adding a project dependency
    The form on the Project dependencies card.

  3. Fill in the form.

    Field What to enter Example
    This project waits for (required) The other project. ERPPA · ERP Rollout – Patel & Associates
    It can start after it finishes or after it starts. after it finishes
    Lag (days) Extra days to wait (negative to overlap). 0
    Why The reason, so others understand the link. Arjun Mehta moves from the ERP rollout to the bank app after go-live
  4. Click “Add”.

Project dependencies card showing a late dependency

The bank app should only start after the ERP rollout ends on 13 November, but it was planned for 12 October, so the link is late 33d.

The card has two lists: Waits for (projects this one depends on) and Needed by (projects that wait for this one). Each link shows the earliest date the project Can start, its planned start and either the slack or how late it is. Remove a link with the bin icon on the waiting project.

What happens next

The link appears as an arrow on the portfolio Roadmap. If it becomes late, it turns red there and counts in the Late dependencies tile.

Common questions

Why don't I see the Portfolios button?

Only people allowed to manage portfolios see it. Everyone with access to the portfolio can still view it and choose an existing portfolio.

Why is a project missing from the portfolio?

You see only the projects you have access to. A private project, or one whose team you are not in, is left out, even if it belongs to the portfolio.

Why is the Budget column empty for some projects?

The budget comes from the project's Budget tab. A project without a budget shows —. See Budget.

Can a dependency make the ERP move a project's dates?

No. Project dependencies only warn you: they show slack or lateness. Change the project's dates yourself if you need to.