Sprint reports: velocity, burndown and burnup¶
The Reports tab answers three questions: how much does the team usually finish (velocity), is the current sprint on track (burndown and burnup), and what happened to the plan (completed, carried over, added and removed work).
Before you start
- Everyone who can see the team can read its reports.
- Velocity appears after the first completed sprint; the sprint report appears once a sprint has started.
Velocity¶
Open Projects → Sprints, click the team and choose Reports. The Velocity chart is at the top.
- Committed is the number of points in the sprint when it started.
- Completed is the points of the items that were Done when the sprint was completed.
A team that regularly completes much less than it commits is planning too much. Use the average velocity shown on the Backlog tab (the average of the last three sprints) as the guide for the next plan. Click the table icon at the top right of the chart to see the numbers.
The sprint report¶
Choose the sprint in the Sprint box. The active sprint is listed first, marked (active), then the completed sprints.
| Figure | What it means |
|---|---|
| Committed | Points in the sprint when it started. |
| Completed (Done so far for the active sprint) | Points of the items that are done. |
| Carried over (Still open for the active sprint) | Items that were not finished. |
| Scope changes | Items added or removed after the start. |
Burndown and burnup¶
- Burndown: the story points still open each day (Remaining) against the Ideal line, which falls evenly from the committed points to zero over the working days. Above the line, the team is behind; below it, the team is ahead.
- Burnup: the points Done against the Total scope. If the scope line rises, work was added during the sprint; that is easier to see here than on the burndown.
Days in the future have no value yet. Click the table icon on either chart to see the numbers for each day.
How the daily points are recorded
The ERP stores one record per day of the sprint: when the sprint starts, when cards move on the Scrum board, when work is added or removed, when the sprint is completed, and every night. Past days can't be filled in afterwards. A sprint that runs normally gets a point every day; in our sample data, which was created in one go, the charts only have a point for the day the data was entered.
Completed, carried over, added and removed¶
Four lists below the charts name the items behind the figures: Completed, Carried over (or Still open), Added after the start and Removed after the start. Click an item key to open it.
Export the report¶
Click Export CSV on the summary card. The file (for example Sprint_2_Accounts-report.csv) opens in Excel or Google Sheets and contains the dates, committed and completed points, the burndown numbers for each day and every item with its result (Completed, Not finished, Added after start or Removed after start).
Common questions¶
Committed points differ from the points on the board
Committed points are frozen when the sprint starts. If work is added or removed later, the board shows today's total and, next to it, Committed at start.
Why does a completed sprint count fewer points than the board showed as done?
Only items that were Done at the moment of Complete sprint count. An item that was approved but not yet completed in the workflow does not.
Where are reports across several projects?
Use Project reports and Project dashboards.