Project reports

Project reports give you the key figures of all your projects and fourteen ready-made reports, from project performance to resource utilisation and budget variance. Pick a period, narrow by project or person, and export any report to Excel, PDF or CSV.

Before you start

  • Open Reports & search → Project reports. You need permission to read project reports.
  • Some reports need extra permissions: people reports (employee productivity), resources, rates (project cost), budgets, risks, sprints and portfolios. A report you can't open is greyed out.
  • Exporting needs the export reports permission.
  • Time needed: about 5 minutes.

Key figures

The page opens on Key figures: tiles that sum up every project you can see.

Key figures for the last 90 days

1 The period, project and person filters, 2 the list of reports.
Tile What it means
Projects How many projects, and how many are active, on hold or completed.
Delayed projects Projects forecast to finish after their planned end date, or whose schedule health is red.
Items Work items, with how many are open and how many were completed in the period.
Overdue items Open items past their due date.
Completion Share of the work done, weighted by estimated effort.
Health score The average health score (0–100) and how many projects are green, amber or red.
Resource utilisation Hours logged divided by the team's capacity.
Budget utilisation Money spent divided by the approved budget, for projects that have a budget.
Upcoming milestones Milestones due in the next 30 days, listed under Next milestones.
High risks Open high risks, with overdue mitigations and late issues.

Filter the figures

  • Period: pick start and end dates, or a preset: Last 30 days, Last 90 days (default), This quarter, This year or Last 12 months.
  • All projects: choose one project.
  • All departments: appears when your organisation has departments.
  • Everyone: choose one person (only for reports about people's work).

Open a report

Click a report name in the list on the left. Each report shows a chart and a table; switch between the chart and the table with the two small icons at the top right of the chart. Click a column heading to sort the table.

Project performance report with a progress chart and a table per project

Project performance: progress, health, overdue items, planned end and forecast finish per project.
Report What it answers
Project performance How far along is each project, is it healthy, and will it finish on time?
Employee productivity Items completed, on-time rate, average cycle time and hours per person.
Department performance Projects, delays, health and output per department.
Task completion trend Items created and completed each week, and the open work left.
Deadline adherence Items and milestones finished on time, late, or missed (still open past due).
Sprint velocity Story points committed and completed per sprint (see Sprint reports).
Resource utilisation Each person's capacity, planned, allocated and logged hours.
Project cost Logged hours multiplied by cost and bill rates, per project.
Budget variance Approved budget against actual, committed and forecast cost (see Budget).
Risk analysis Open risks, risk exposure and issues per project (see Risks & issues).
Portfolio Every project with health, priority, dates and progress.
Portfolios and programmes Projects, health, progress, budget and late dependencies per portfolio (see Portfolio).
Project dependencies Which project waits for which, with the slack or delay in days.
Planned vs actual Baseline finish and effort against the forecast and the hours logged (see Gantt and schedule).

A note under each table explains how the numbers are calculated.

Employee productivity report

Employee productivity. The ERP reminds you to use it to spot overload and blockers, not to rank people.

Resource utilisation report

Resource utilisation: capacity is working hours minus holidays and time off; logged is the time entries.

Planned vs actual report

Planned vs actual compares each project with its latest baseline, for example Original plan.

Export a report

  1. Open the report and set the filters.
  2. Click Export at the top right.

    Export menu with CSV, Excel and PDF
    1 Choose the file format.

  3. Choose CSV, Excel or PDF. The file downloads with the same filters as the screen.

The Export button appears only on a report (not on Key figures) and only if you have the export permission.

Health settings

Every project gets a health score from 0 to 100. It is the weighted average of schedule (50), risks and issues (30) and resources (20); cost and scope count too when the project has a budget and change requests. The score becomes Green, Amber or Red using two thresholds.

Health thresholds settings

With these settings a score of 75 or more is green, 50 to 74 amber and below 50 red.

Administrators (with the manage PMS settings permission) see Health settings at the bottom of the report list:

  1. Click Health settings.
  2. Enter Green from (for example 75) and Amber from (for example 50). Scores below the amber threshold are red.
  3. Click Save.

A project manager can also override the health of one project for a while, with a reason, on the project's Overview (see The project workspace).

Common questions

A report is greyed out

You don't have the permission it needs, or the feature it reports on isn't in use. Hover over the name to see the description; ask your administrator for access.

Why does a project show 100 % progress when it still has open tasks?

Progress is weighted by estimated effort. When only some items have an estimate, those items decide the percentage. Give every item an estimate (on the task's Dates and effort) to get a fair figure.

Can I schedule a report by e-mail?

Not from this page. Build a dashboard with the reports you check often, or export the report when you need it.

Which projects are included?

Only the projects you can see. Archived projects are excluded from the portfolio reports.